Key projects we've worked on

Client Olympic Delivery Authority
Contractor Bow East Logistic Centre/ RFS Works Limited
Date 2008 - 2012
Volume Circa 350,000 tonnes
Unloading and loading of aggregates to supply the Olympic Park construction site and associated concrete plants.

Utilised largest what was at the time our materials handler in the fleet and what was the largest clamshell grab in operation on UK rail network.

2 No materials handlers working in tandem to discharge up to 5No 1500 tonne trains per 24hr shift.

2No loading shovels re-handling to stockpiles and loading out of circa 7000 tonnes per day.

Working within strict timetables and delivery demands